NEWBURY RACECOURSE

 

Year: 2014-2015

Location: Newbury

Contractor: MIDWEST Formwork Ltd.

 

Reinforced Concrete Frame Building on 5 levels. Our responsibility was to mark and survey everything regarding the structure from the moment the piling company was done.

 

Responsibilities:

  • Pilecaps
  • Ground Beams
  • Column Starter bars
  • Slab edges, Openings
  • Levels, Datums
  • Walls, Columns
  • Volume Estimation
  • As-Built Drawings

ROSEBOURNE GARDENS

 

Year: 2015-2016

Location: Andover

Contractor: Barnwood Construction Ltd.

 

 

Steel Frame Commercial Building. Working for the main contractor.

 

Tasks:

  • Foundation
  • Holding Down Bolts
  • Column Starter bars
  • Slab edges, Openings
  • Levels, Datums
  • Walls, Columns
  • Volume Estimation
  • As-Built Drawings

As the Steel Frame building was manufactured overseas the accuracy of the project was critical.

CAPITAL QUARTER

 

Year: 2017-2018

Location: Cardiff

Contractor: MIDWEST Formwork Ltd.

 

 

RC Frame Student Accomodation on 25 stories with slipform core.

 

Responsibilities:

  • Column Starter bars
  • Slab edges, Openings
  • Levels, Datums
  • Walls, Columns
  • Volume Estimation
  • As-Built Drawings